skip to main
|
skip to sidebar
Raising the Back Canaan Manor
Wednesday, July 28, 2010
Goodbye Ledge, Hello Foundation Prep
With the ledge cleared out, stone was filled and the footing forms are in place. Footings will be poured tomorrow! Check out the pics.
1 comment:
Mrs. Halla
July 31, 2010 at 9:20 AM
It looks great so far Katie. I can't wait to follow the progress.
Reply
Delete
Replies
Reply
Add comment
Load more...
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
►
2011
(3)
►
February
(1)
►
January
(2)
▼
2010
(22)
►
November
(3)
►
October
(2)
►
September
(6)
►
August
(5)
▼
July
(4)
Footings poured, Forms up
Goodbye Ledge, Hello Foundation Prep
Driveway in the rough
Site work underway
►
May
(2)
►
2009
(4)
►
December
(3)
►
November
(1)
Contributors
Mike
Ms. Martin
It looks great so far Katie. I can't wait to follow the progress.
ReplyDelete